Experts of Branch of SMU-9 of Northern Construction Department go on concreting the steam cell of Power Unit 2 of the LNPP under construction
|
2017-04-20 |
Installation of the modular construction camp started
|
2017-04-19 |
Start of the Power Unit 1 reactor plant cold and hot run at the Leningrad NPP under construction
|
2017-04-13 |
Employees of the branch of SMU-9 of Northern Construction Department continue construction of the third cooling tower at the Leningrad NPP construction site
|
2017-04-10 |
Specialists of JSC MSU-90 install reactor coolant pump body in the Power Unit 2 reactor building
|
2017-04-04 |
JSC CONCERN TITAN-2 Finnish partners from FENNOVOIMA OY familiarize themselves with progress of construction of the new Power Units
|
2017-03-28 |
Erection electricians of the Third Unit of JSC SEM installed integral generator circuit breakers in the turbine building of Power Unit 1 of the LNPP under construction
|
2017-03-27 |
MSU-90 first unit experts have installed two decontaminating baths in the auxiliary building of the first power unit of the LNPP under construction.
|
2017-03-24 |
JSC SEM third unit experts are close to complete the installation of bus duct branching from 24 kV main bus duct to the auxiliary transformers near the turbine building of the LNPP under construction
|
2017-03-22 |
Installation of Manitowok 18000 crawler crane is under way at the Leningrad NPP construction site
|
2017-03-21 |
The first unit of JSC "SEM" perform large-scale works at the facilities of the first power unit of the LNPP under construction
|
2017-03-20 |
Titan-2 signs contract with Ab Tallqvist Infra Oy
|
2017-03-16 |
JSC "MSU-90" work on in the steam chamber building of the first power unit of the LNPP under construction
|
2017-03-13 |
Steam reheater and steam separation systems in the Turbine Building of Unit 1 at the Leningrad NPP site successfully passed hydraulic tests
|
2017-03-03 |
New contracts on Hanhikivi 1 site
|
2017-03-01 |
Earth works continue at the Hanhikivi-1 site to build accommodation camp
|
2017-02-28 |
JSC CONCERN TITAN-2 participated in an international recruitment event in Oulu, Finland
|
2017-02-27 |
Subsidiaries of the holding "TITAN-2" are preparing for cold and hot run of the first power unit reactor plant for the LNPP under construction
|
2017-02-20 |
The third unit of JSC MSU-90 АО MSU-90 brought out the generator rotor from stator in the turbine building of the first power unit of the LNPP under construction
|
2017-02-14 |
The third unit of JSC SEM proceeds installation of 24 kV isolated phase bus duct
|
2017-02-09 |
A working meeting was held in Helsinki for the members of the Hanhikivi-1 NPP construction project
|
2017-02-03 |
Emergency Power Supply Diesel Generators Prepared for Comprehensive Tests
|
2017-02-01 |
Specialists of JSC "MSU-90" performed a number of important operations at the construction site of the Leningrad NPP
|
2017-01-24 |
Specialists of the subsidiary companies of the holding "TITAN-2" completed overturning of the housing of the main circulation pump of Power Unit 2 of the Leningrad NPP under construction.
|
2017-01-18 |
Installation of chemical water treatment tanks for Power Unit 2 of the Leningrad NPP under construction began
|
2017-01-13 |
Specialists of unit No. 2 of JSC "MSU-90" are working on technological trestles of the Leningrad NPP under construction
|
2017-01-12 |
RBK magazine’s fake about the co-owner of JSC "CONCERN TITAN-2" in "50 fastest growing companies"
|
2016-12-30 |
Turbine of Power Unit 1 of the LNPP under construction was set on the shaft turning installation
|
2016-12-27 |
Reactor coolant pumps electric motors idling started
|
2016-12-23 |
Opening of Holding "TITAN-2"-based nuclear industry SRO training centre
|
2016-12-22 |
Getting through with the work on transformer platform
|
2016-12-20 |
Work in the Relay panel building is close to completion
|
2016-12-19 |
Teleconference: Sosnovy Bor– Pyhäjoki
|
2016-12-16 |
Simulators Charging
|
2016-12-13 |
Equipment Assembling
|
2016-12-06 |
Titan-2 signs contract on the construction of site offices and social spaces
|
2016-12-05 |
Guests from Finland
|
2016-11-30 |
Tendon Strands
|
2016-11-28 |
New Training Center
|
2016-11-23 |
Switch Chamber
|
2016-11-21 |
Reactor Building
|
2016-11-18 |
Preparing to Supply Power
|
2016-11-17 |
Entered into Force a Ban on Flights over Hanhikivi Peninsula
|
2016-11-10 |
Oil System Preparation
|
2016-11-08 |
Equipment Test
|
2016-11-03 |
Meeting in Finland
|
2016-10-31 |
Best in Electric Installation Operations
|
2016-10-24 |
Holding “TITAN-2” Shared Experience with Turkish Guests
|
2016-10-21 |
1,400 people visited the open doors day
|
2016-10-21 |
For Nuclear Fuel Refueling
|
2016-10-19 |