Top managers of JSC CONCERN TITAN-2 won Rosatom’s “Person of the Year 2017” contest
|
2018-04-28 |
Specialists of JSC MSU-90 proceeded with welding of the reactor coolant pipeline in the reactor building of the second power unit of the LNPP under construction
|
2018-04-25 |
Personnel of the Holding’s subsidiary companies continues to install reactor building equipment
|
2018-04-24 |
Heads of the Finnish construction companies forming part of the FinNuclear Association paid a visit to the TITAN-2 Holding
|
2018-04-20 |
Polar crane beam was installed at the Leningrad NPP construction site
|
2018-04-19 |
The TITAN-2 Holding took part in the all-Russian career guidance campaign “Week without turnstiles”
|
2018-04-17 |
Four hydraulic accumulators of the emergency core cooling system (ECCS) were delivered to the construction site of the second power unit of the LNPP under construction
|
2018-04-16 |
Seminar of the Raahe Association of Entrepreneurs dedicated to the contract work was held in the Hanhikivi-1 NPP construction area
|
2018-04-12 |
Employees of JSC MSU-90 Workshop No. 3 are working on high-pressure feed pumps
|
2018-04-10 |
Preparation for installation of high and low pressure valves is in progress in the turbine building of the second power unit of the LNPP under construction
|
2018-04-09 |
Specialists of JSC MSU-90 continue to assemble the turbine unit at the second power unit of the LNPP under construction
|
2018-04-06 |
Specialists of the TITAN-2 Holding subsidiaries are preparing for welding of the reactor coolant pipelines
|
2018-04-04 |
Works at the regional volleyball centre construction site in Sosnovy Bor are ongoing
|
2018-04-02 |
Tour for the Northern Building Directorate office employees took place at the construction site of the Leningrad NPP
|
2018-03-28 |
Employees of the TITAN-2 Holding were awarded for successful work
|
2018-03-27 |
Employees of the Leningrad Nuclear Power Plant proceeded with commercial pilot operation of the new unit.
|
2018-03-26 |
Delegation from Hungary visited production facilities of the TITAN-2 Holding
|
2018-03-23 |
New power unit of the Leningrad NPP was successfully integrated into the unified energy system of Russia
|
2018-03-12 |
Chemically purified water tanks are being installed at the site of the second power unit of the LNPP under construction
|
2018-03-07 |
JSC "MSU-90" installed the low-pressure rotor in the turbine building at the LNPP Power Unit 2
|
2018-03-06 |
JSC MSU-90 installed the electric feed pumps in the Turbine building of the LNPP Power Unit 2
|
2018-03-05 |
Successful trial run of the turbine at the new LNPP Power Unit
|
2018-03-02 |
The Installation of New LED Lighting on the Sosnovy Bor Schools Grounds is under way
|
2018-02-27 |
Power Unit 2 of LNPP under Construction Being Prepared for Turbine Rotors Installation
|
2018-02-19 |
Contracting Company JSC MSU-90 Started Assembling the Dome Part of the Reactor Building Inner Containment at Power Unit 2 of the LNPP under Construction
|
2018-02-13 |
Low Pressure Cylinder Rotor Delivered to the Power Unit 2 Turbine Building of the Leningrad NPP under Construction
|
2018-02-12 |
JSC MSU-90 Continues Installing Reactor Plant Equipment on the LNPP Construction Site
|
2018-02-08 |
Aleksandr Tupitsyn, the Hanhikivi-1 NPP Construction Director in JSC CONCERN TITAN-2, Delivered Reports at the Polytechnic University of Milan
|
2018-02-07 |
The New Power Unit Reactor of LNPP has been Brought to the Minimum Controlled Power Level Today
|
2018-02-06 |
JSC SEM Prepares to Start Welding Reactor Coolant Pipelines
|
2018-02-02 |
JSC Sosnovoborelektromontazh Installs a Modern Lighting System on Sosnovy Bor Schools Facades.
|
2018-02-01 |
JSC MSU-90 Continues Extensive Works in the Power Unit 2 Turbine Building of LNPP under Construction
|
2018-01-31 |
The Veterans of the Nuclear Society of Finland (ATS Senior) Visited the Construction Site of the New LNPP Power Units
|
2018-01-30 |
Northern Construction Department Completed Concreting Part of Inner Containment of Reactor Building at Power Unit 2 of LNPP under Construction.
|
2018-01-26 |
TEREX Tower Crane Telescoping is under Way on LNPP Power Unit 2 Construction Site
|
2018-01-25 |
Northern Construction Department Prepares for Further Concreting of Evaporative Cooling Tower at LNPP-2 Construction Site
|
2018-01-16 |
Holding Company Subsidiaries Assemble Inner Containment Dome Liner of Reactor Building for Power Unit 2 of LNPP-2
|
2018-01-15 |
Generator Stator Installed in the Turbine Building of the Power Unit 2 of the Leningrad NPP under Construction
|
2017-12-29 |
Nuclear Fuel Loading into Reactor Completed in the Power Unit 1 of LNPP-2
|
2017-12-18 |
“Safety Culture Day” at the Hanhikivi-1 NPP Construction Site
|
2017-12-12 |
The Reactor First Criticality Started at Power Unit 1 of the Leningrad NPP
|
2017-12-08 |
PJSC SUS Team Completed Assembling the Polar Crane Elements for the Reactor Building of the Power Unit 2 of the Leningrad NPP under Construction.
|
2017-12-06 |
JSC SAM Fourth Unit Specialists Reconstructing 330 kV Overall Plant Switchgear of LNPP-1
|
2017-12-04 |
Holding Company Subsidiaries’ Teams Carried out Unique Installation Operation at the LNN Construction Site.
|
2017-11-30 |
Nuclear Construction Conference Held in Moscow.
|
2017-11-29 |
Four New Radiation Monitoring Points Installed in Sosnovy Bor
|
2017-11-27 |
JSC SEM Experts Carry out Works in Power Unit 1 of the LNPP under Construction
|
2017-11-24 |
The Delegation from Finnish Twin Cities of Pyhäjoki, Kalajoki, and Raahe Arrived in Sosnovy Bor
|
2017-11-23 |
TITAN-2 Holding Company Once Again Became One of Top-50 Most Fast-Growing Russian Companies
|
2017-11-17 |
Reactor Vessel for the Power Unit 2 of the Leningrad NPP under Construction Delivered to Sosnovy Bor from Izhora Plants
|
2017-11-15 |