TITAN-2 Holding Employees to Attend the VII Divisional Championship REASkills-2023
|
2023-04-10 |
License Obtained for the Construction of the Third Power Unit of the El-Dabaa NPP in Egypt
|
2023-03-31 |
Holding TITAN-2 has Started Construction of Training Centre in Kurchatov
|
2023-03-23 |
Important Equipment is Delivered to the PDEC Proryv Site in Seversk
|
2023-03-21 |
Specialists of JSC CONCERN TITAN-2 in Kurchatov Continue the Works at the Kursk NPP-2 Construction Site
|
2023-03-17 |
Titan-2 Holding is Carrying Out the Construction of Data Processing and Storage Center in the Republic of Tatarstan (Data Processing Center Innopolis)
|
2023-03-14 |
The preparatory period works continue at the construction site of the Leningrad NPP power units 3 and 4
|
2023-02-22 |
JSC CONCERN TITAN-2 specialists successfully completed installation of the turbine building roof at power unit 2 of the Kursk NPP-2
|
2023-02-20 |
CONCERN TITAN-2 commenced the transformer substation construction works at the construction site of the Leningrad NPP units 7 and 8
|
2023-02-14 |
CONCERN TITAN-2 will be the main developer of a new housing complex in Sosnovy Bor
|
2023-02-13 |
Manufacture of metal structures for the AKKUYU NPP continues at the construction base of TITAN TECHNOLOGY PIPELINE (LLC TPL)
|
2023-02-13 |
JSC CONCERN TITAN-2 and the Tomsk state university of architecture and building agreed on cooperation
|
2023-02-09 |
The cantilever truss was installed in the reactor hall of the AKKUYU NPP third power unit
|
2023-02-02 |
JSC CONCERN TITAN-2 specialists continue works at the facilities of the future eco-technoparks in the Kirov oblast and the Udmurt Republic
|
2023-01-27 |
Eight hydraulic accumulators of the passive core flooding system (pcfs) were installed in the first power unit of the AKKUYU NPP under construction in Turkey
|
2023-01-18 |
The winter student labour shift commenced in TITAN-2 HOLDING
|
2023-01-17 |
The dome of inner containment of the reactor building was installed at the Akkuyu NPP power unit No. 1
|
2023-01-11 |
The works on concreting the pumping station foundation have commenced at the LNPP construction site
|
2022-12-20 |
A bridge crane of the turbine building has been set up at the Akkuyu NPP power unit No. 1
|
2022-12-14 |
TITAN-2 Holding representatives have attended ATOMEXPO International Forum
|
2022-12-09 |
JSC CONCERN TITAN-2 completed the construction of the new kindergarten in Sosnovy Bor in 2022
|
2022-11-18 |
Railway reconstruction is being performed by JSC CONCERN TITAN-2 in industrial zone of Sosnovy Bor
|
2022-11-03 |
The works on construction of the integrated fire fighting pumping station are being performed by JSC CONCERN TITAN-2
|
2022-10-21 |
The TITAN-2 Holding specialists have become the winners of the nomination “Best Construction Site” at World Construction Championship II in Kazan
|
2022-10-08 |
Reactor vessel of Power Unit No. 2 has been installed at the Akkuyu NPP construction site in Turkey
|
2022-09-23 |
The contract for construction of new power units of Leningrad NPP has been signed
|
2022-08-17 |
The main stage of construction of the first Power Unit has commenced at El-Dabaa NPP in Egypt
|
2022-07-21 |
Specialists of JSC CONCERN TITAN-2 have proceeded to installation of truss units of the turbine building of Power Unit No. 2 of Kursk NPP-2
|
2022-07-07 |
Tier 3 of the inner containment (IC) of the reactor building of Power Unit No. 2 of Akkuyu NPP (the Republic of Turkey) has been installed
|
2022-06-23 |
Next batch of metalwork for Akkuyu NPP has been shipped
|
2022-06-16 |
Welding operations at the reactor coolant pipeline of Power Unit No. 1 of Akkuyu NPP (the Republic of Turkey) have been completed
|
2022-06-03 |
Concreting of the foundation slab for the turbine building of Akkuyu NPP Power Unit No. 4 has started in the Republic of Turkey
|
2022-05-30 |
Construction of onshore facilities continues at the Akkuyu NPP in Turkey
|
2022-04-29 |
General director of TITAN-2 holding assessed the PDEC PRORYV construction progress
|
2022-04-21 |
TITAN-2 Holding Team has participated in REASKILLS 2022 Championship
|
2022-04-18 |
Welding of the reactor coolant pipeline started at the reactor building of the Akkuyu NPP first Power Unit
|
2022-03-22 |
ANOTHER BATCH OF STEEL STRUCTURES WAS SHIPPED IN THE END OF FEBRUARY FROM THE WORKSHOPS OF LLC TITAN TECHNOLOGY PIPELINE (LLC TPL) FOR THE AKKUYU NPP CONSTRUCTED IN TURKEY
|
2022-03-18 |
Installation of the reactor plant main equipment at the first Power Unit of the Akkuyu NPP has been completed
|
2022-03-10 |
LLC TITAN TECHNOLOGY PIPELINE (TPL), a subsidiary of TITAN-2 Holding, manufactures steel products for the third Power Unit of the Akkuyu NPP
|
2022-03-09 |
The fifth tier of inner containment of the reactor building was installed at power unit No. 1 of the Akkuyu NPP (Turkey)
|
2022-01-17 |
At the construction site of the Shared Research Facility "SKIF" works of the preparatory period are underway
|
2022-01-12 |
Specialists of JSC CONCERN TITAN-2 continue working at the site of “Proryv” project in the city of Seversk of the Tomsk Region
|
2022-01-11 |
JSC CONCERN TITAN-2 continues the construction of a new kindergarten in Sosnovy Bor
|
2021-12-24 |
Builders of the Russian-Turkish Joint Venture TİTAN 2 IC İÇTAŞ İNŞAAT ANONİM ŞİRKETİ (T2IC) commenced construction of the foundation slab of the Power Unit 1 pumping station of the Akkuyu NPP
|
2021-12-17 |
Builders of JSC CONCERN TITAN-2 laid the last concrete of this year at the Dudinsk oil storage depot
|
2021-12-07 |
The TITAN-2 has shipped steel structures for the Akkuyu NPP
|
2021-11-29 |
Specialists of JSC CONCERN TITAN-2 have completed grouting of the reactor building foundation slab of power unit BREST-OD-300 (БРЕСТ-ОД-300)
|
2021-11-24 |
The representatives of the Nuclear Regulatory Agency of the Republic of Turkey (NDK) visited the TITAN-2 Holding
|
2021-11-15 |
JSC CONCERN TITAN-2 is participating in the El Dabaa NPP Construction Project in Egypt
|
2021-11-02 |
The License for construction of Akkuyu NPP power unit 4 has been obtained
|
2021-11-01 |