Currently, preliminary alignment of the shafting lines has been completed.

In order to start alignment of the wheel space using laser equipment, the rotors were removed from the bearing assembly bushings and installed in the shipping supports.

Necessary measurements of equipment parameters are carried out. A measurement report has been made and two high-pressure valves have been inspected.

Elements of the wheel space (diaphragm, seal boxes, inner cylinders) have been shipped to the installation area. The generator stator rotor weighting approximately 100 tons is being prepared for installation, and its de-preservation is in progress.

According to the installation schedule, the device for wheel space laser alignment will be delivered to the site in mid May.

Note:

Titan-2 Holding is the largest in the North-West group of companies, constructing the most important nuclear industry and power facilities. The company performs a full range of construction and installation works from engineering to commissioning.

Titan-2 Holding is the general contractor for the construction of the Leningrad NPP-2 power units. The Holding Companies perform all the civil, installation, and electrical works at a construction site. The works are carried out in the reactor, turbine, power supply, water supply, heat cogeneration buildings and other power unit structures.

The Holding is the main contractor for the construction of the Hanhikivi-1 NPP in Finland.