In connection with the incident, which happened early Thursday morning, dredging works has been stopped on the Hanhikivi peninsula.

The specialists of OJSC “SUS” completed the pre-assembly work of the 4th tier of the reactor building inner containment for the second Power Unit of the LNPP under construction.

Two main circulation pump sets have been delivered to the construction site of the Leningrad NPP. Specialists of the First Unit of JSC “MSU-90” unloaded the equipment near the reactor building of the second Power Unit.

The specialistы of the Second Unit of JSC “MSU-90” installed thrust truss in the reactor building of the second Power Unit of the LNPP under construction.

The tests of the concrete structures for the turbine cooling water supply system are going on at the Leningrad NPP construction site. The tests are conducted under supervision of the specialists of JSC “CONCERN TITAN-2”.

Specialists of the Third Unit of JSC “MSU-90” keep on installing the equipment in the pumping station building at the Leningrad NPP site. The main function of the facility is to provide the system with water to cool the turbine condenser.

Specialists of SMU-1 of “Northern Management for Construction” poured 180 m3 of concrete at the inner containment of the reactor building for the second Power Unit of the LNPP under construction.

Erection electricians of the Second Unit of JSC “EM” completed the installation of cable metalwork of the five galleries for personnel and cables, and two cable ducts that connect essential facilities of the NPP under construction

Specialists of the Second Unit of JSC “MSU90” are completing their equipment installation operations at one of the facilities of the LNPP under construction.