The images will become the new symbols of the construction of the third and fourth power units of Leningrad NPP-2.

On the construction site of Phase 2 of the Kursk NPP, specialists of TITAN-2 Holding are involved in building several facilities for Power Unit 2: in the turbine building, at the construction of the evaporative cooling tower, at the training centre, and at the fire station.

Once the concreting of the envelope of the evaporative cooling tower was completed, TITAN proceeded straight to building the precast reinforced concrete frame for the subsequent installation of sprinklers and water catchers. The winter pipeline and the trunk pipeline are being installed here as well.

At the fire station, JSC CONCERN TITAN-2 has built a complex of buildings and structures designed to ensure fire safety of the Kursk NPP-2 power units under construction. The complex has been commissioned for temporary operation of the fire station.

In Kurchatov, the company continues building the training centre for Kursk NPP-2. The pile foundation with bored piles has been built as well as the foundation slab of the buildings. The walls of the underground part are being erected. JSC CONCERN TITAN-2 is the General Contractor for the “turnkey” construction of the training centre, including the supply and installation of equipment. The training centre is to be completed and put into operation in late 2024.On the construction site of Phase 2 of the Kursk NPP, specialists of TITAN-2 Holding are involved in building several facilities for Power Unit 2: in the turbine building, at the construction of the evaporative cooling tower, at the training centre, and at the fire station.

Once the concreting of the envelope of the evaporative cooling tower was completed, TITAN proceeded straight to building the precast reinforced concrete frame for the subsequent installation of sprinklers and water catchers. The winter pipeline and the trunk pipeline are being installed here as well.

At the fire station, JSC CONCERN TITAN-2 has built a complex of buildings and structures designed to ensure fire safety of the Kursk NPP-2 power units under construction. The complex has been commissioned for temporary operation of the fire station.

In Kurchatov, the company continues building the training centre for Kursk NPP-2. The pile foundation with bored piles has been built as well as the foundation slab of the buildings. The walls of the underground part are being erected. JSC CONCERN TITAN-2 is the General Contractor for the “turnkey” construction of the training centre, including the supply and installation of equipment. The training centre is to be completed and put into operation in late 2024.

For information:

The TITAN-2 Holding is a Russian group of companies that builds nuclear facilities. Organisations of the Holding perform the whole cycle of works, from development of basic design documentation to facility commissioning.

The TITAN-2 Holding is the general contractor for construction of the new power units of the Leningrad NPP. At the construction site, the organisations of the Holding perform all civil construction, installation, and electric installation works.

The Holding participates in the construction of Akkuyu NPP in Turkey, Paks II NPP in Hungary and El-Dabaa NPP in Egypt. 

The future rehabilitation centre is located in Berdsk, Novosibirsk Region. The customer for the construction is the Public Law Company SINGLE CUSTOMER FOR CONSTRUCTION.