The installation of the stator in the pre-design position required high precision and the use of tailored rigging and hydraulic systems.

Preparations for the operation included a complex of engineering works, that is reinforcement of the machine room floors, installation of temporary support structures and arrangement of a special rail track for transporting equipment to the installation site.

The specialists lifted the stator to a +18.5 meters elevation. The operation was carried out without cranes using a hydraulic rigging system with constant geodetic control.

Konstantin Goldebayev, Project Manager for the construction of the T2IC turbine island:

“The installation of the stator in the pre-design position at Power Unit 2 is a milestone. This is one of the heaviest and most dimensional components of a turbine generator, so it is extremely important that the construction part, temporary structures and installation technology work as a single system. Any deviations at this stage immediately affect the subsequent equipment alignment and assembly. Thus, the exact design position confirms the quality of the work carried-out and the readiness of the machine hall for all subsequent installation operations”.

Aleksandr Zlobin, Job Superintendent of the installation area, TSM Enerji Turbine Island Department:

“Based on the experience gained while working at the NPP Power Unit 1, we have successfully applied our accumulated expertise here. Due to this, the installation of the turbine generator stator at Power Unit 2 has been completed on schedule and in full compliance with all safety requirements. The main challenge was an extremely tight deadline, which required us to be extremely precise and efficient in installing the hydraulic gantry system”.

For information:

The TITAN-2 Holding is a Russian group of companies that builds nuclear facilities. Organisations of the Holding perform the whole cycle of works, from development of basic design documentation to facility commissioning.

The TITAN-2 Holding is the general contractor for construction of the new power units of the Leningrad NPP. At the construction site, the organisations of the Holding perform all civil construction, installation, and electric installation works.

The Holding participates in the construction of Akkuyu NPP in Turkey, Paks II NPP in Hungary and El-Dabaa NPP in Egypt.