The employees of the TITAN-2 Holding subsidiaries were engaged in construction and successful preparation of the new LNPP power unit with the VVER-1200 reactor for commissioning.

The reactor thermal power was raised up to the level of 35% from the rated one to connect the generator into the grid. The turbine speed was 3000 rotations per minute.

The power unit was connected to the power grid at the minimal level of electrical power of 240 MW. The pilot operation phase started.

Background information:

TITAN-2 Holding is a Russian group of companies building nuclear facilities. Holding companies perform a full cycle of work - from the design documentation development to the commissioning of the facility.

Holding TITAN-2 is a General Contractor for the construction of new power units of the Leningrad Nuclear Power Plant. Holding companies perform all general construction, installation and electrical work at the construction site.

The Holding is a main Contractor for the construction of the Hinhikivi-1 NPP in Finland and the Akkuyu NPP in the Republic of Turkey.