In January, 2016 the crew started works to prepare cables and equipment for 10 kV power supply under the constant scheme into the buildings: power supply of normal operation, control building, reserve diesel power station, unit diesel power station and water preparation building.

Preparation includes installation of 10 kV cable sleeves, laying of control cables and installation of secondary circuits. These works are carried out within the framework of execution of the target task of flowing at the decompressed reactor.

At the end of January, it is planned to provide power supply to 10 kV sections of normal operation power supply building and then to the power equipment of buildings which are involved in flowing.

Note:

The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.

The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.