Shaft line and turbine cylinders were aligned. The unit is installed onto the permanent pads; concreting is ongoing.

Concrete having reached its designed strength, the specialists will commence wheel space alignment. The turbine will be again almost fully disassembled during this process. Multiple disassembly and further assembly are required to ensure perfectly precise jointing of all the turbine components.

Laser equipment will be applied during alignment. The activity is planned to be finalized by this November. The turbine will further be installed onto the barring gear, i.e. rotated in the idle mode, allowing the specialists to check the turbine assembly quality.

The installation onto the barring gear precedes the vacuum build-up. Upon that, almost whole turbine unit will become operational.

Note:

Titan-2 Holding is the largest in the North-West group of companies, constructing the most important nuclear industry and power facilities. The company performs a full range of construction and installation works from engineering to commissioning.

Titan-2 Holding is the general contractor for the construction of the Leningrad NPP-2 power units. The Holding Companies perform all the civil, installation, and electrical works at a construction site. The works are carried out in the reactor, turbine, power supply, water supply, heat cogeneration buildings and other power unit structures.