Each diesel engine-generator unit that is 12 metres long and weighs 140 tons was unloaded by means of “Liebherr LR 11350”. This critical operation was done by specialists of the assembly site of tower and bridge cranes of JSC "UAT".

In front of the building of diesel station, diesel engine-generator units were unloaded to a special platform. And then the equipment was rolled by tracks to its regular place in the building. The speed of moving of the heavy structure was one metre per hour.

There will be the total of 4 diesel engine-generator units in the building of diesel power station. Two more units of equipment are planned to install later.

Specialists will have to equip diesel engine-generator units with cooling systems, compressors, receivers etc. Large-sized auxiliary equipment will be installed to its regular place through the building roof. Afterwards, assembly apertures in the roof will be closed.

Note:

The Holding “Titan-2” is the largest in the North-West group of companies, erecting the most important objects of the nuclear industry and energy. The organization performs a full range of construction and installation works from engineering to commissioning.

The Holding “Titan-2” is one of the main contractors for the construction of power units No. 1 and No. 2 of the Leningradskaya NPP-2. Main organizations of the company perform 30% of general construction and 80% of installation works on the site. Specialists of the holding are engaged on the objects of the Leningradskaya NPP-2 first and second power units. The works are being performed in the buildings of the reactor, turbine, electricity, water, heating system and other structures of power units.